Question:
user has changed the setting in the order form to require a deadline for each order, and also checked the option to copy deadline from order for the project. This copies over fine, but the deadline is not carried over to the specific jobs and the translators are not getting the deadline information automatically. Is there a way to make this automatic?
Answer:
That is correct that after ticking the option to copy the deadline from order to project it is only copied to the project, not specific jobs since deadlines for specific jobs are set by the manager when assigning jobs and it would not make sense to copy the project/order deadline automatically into the specific jobs.